Young-Davidson Reports Underground Cash Costs of $656 per Ounce and
Underground Unit Costs of $41 per Tonne
TORONTO, Oct. 14, 2014 /CNW/ - AuRico Gold Inc. (TSX: AUQ) (NYSE: AUQ), ("AuRico" or the "Company") today announces preliminary third quarter
production results. All amounts are in U.S. dollars unless otherwise
indicated. (Results for the third quarter 2014 are estimates only and are subject
to change.)
AuRico is reporting its ninth consecutive quarter of record company-wide
gold production driven by record production from the cornerstone
Young-Davidson mine. Period-over-period production growth is expected
to continue going forward, underpinned by the ongoing ramp-up in
production at the Young-Davidson mine located in northern Ontario.
To view "Company Wide Quarterly Production Growth", please click:
http://files.newswire.ca/975/aurico_1014.pdf
Preliminary 2014 Third Quarter Operational Results
|
|
Q1/13
|
Q2/13
|
Q3/13
|
Q4/13
|
Q1/14
|
Q2/14
|
Q3/141
|
|
Young-Davidson
|
|
|
|
|
|
|
|
|
Gold ounces produced2
|
28,281
|
29,252
|
30,099
|
33,106
|
35,104
|
40,166
|
40,538
|
|
|
Underground cash costs per gold ounce
|
-
|
-
|
-
|
$663
|
$808
|
$803
|
$656
|
|
|
Open pit cash costs per gold ounce
|
$694
|
$716
|
$666
|
$983
|
$1,350
|
$974
|
$923
|
|
Total cash costs per gold ounce3
|
$694
|
$716
|
$666
|
$850
|
$1,009
|
$871
|
$723
|
|
Underground mine
|
|
|
|
|
|
|
|
|
|
Tonnes mined per day
|
1,130
|
1,611
|
1,417
|
2,590
|
2,611
|
3,595
|
3,752
|
|
|
Grades (g/t)
|
2.7
|
2.5
|
2.8
|
3.1
|
2.8
|
3.3
|
3.1
|
|
|
Development metres
|
1,941
|
2,445
|
2,620
|
2,986
|
3,772
|
3,545
|
3,269
|
|
Mill processing facility
|
|
|
|
|
|
|
|
|
|
Tonnes processed per day
|
6,466
|
7,017
|
6,747
|
6,969
|
7,163
|
8,230
|
7,670
|
|
|
Grades (incl. open pit stockpile)
|
1.8
|
1.7
|
1.7
|
2.0
|
1.8
|
2.2
|
1.9
|
|
|
Recoveries (%)
|
86%
|
85%
|
89%
|
88%
|
87%
|
88%
|
90%
|
|
El Chanate
|
|
|
|
|
|
|
|
|
Gold ounces produced
|
17,889
|
18,751
|
18,804
|
16,420
|
19,110
|
16,032
|
16,499
|
|
Total cash costs per gold ounce3
|
$563
|
$602
|
$588
|
$615
|
$586
|
$618
|
$663
|
|
Open pit tonnes mined per day
|
106,319
|
98,928
|
87,336
|
98,487
|
95,402
|
93,808
|
94,643
|
|
Consolidated Results
|
|
|
|
|
|
|
|
|
Gold ounces produced2
|
46,170
|
48,003
|
48,903
|
49,526
|
54,214
|
56,198
|
57,037
|
|
Total cash costs per gold ounce3
|
$635
|
$655
|
$628
|
$771
|
$870
|
$801
|
$706
|
1. Data provided for the third quarter 2014 are estimates only and
subject to change.
2. Includes pre-production gold ounces from the Young-Davidson
underground mine prior to the declaration of commercial production in
the underground mine on October 31, 2013.
3. Represents a non-GAAP measure. See page 18 of the Company's Q2 2014
Management's Discussion & Analysis for further information. Cash costs
are prior to inventory net realizable value adjustments & reversals.
For Young-Davidson, gold ounces for cash costs purposes include ounces
produced for 2013, and ounces sold for 2014. For El Chanate and on a
consolidated basis, gold ounces for cash cost purposes include ounces
sold. Pre-production ounces produced at Young-Davidson are excluded
from ounces produced as these ounces were credited against capitalized
project costs when sold.
|
"The Company is pleased to report its ninth consecutive quarter of
record company-wide gold production, which builds on the successes
achieved in prior quarters. We are particularly encouraged that our
operation teams have delivered another strong quarter of production and
demonstrated that their focus remains on quality production that drives
margins, with Young-Davidson reporting a significant 17% decrease in
cash costs", stated
Scott Perry
, President and Chief Executive Officer.
He continued, "The disciplined approach to our business underpins our
growing production profile, which combined with our decreasing cost
profile, positions the Company for long-term, sustainable performance.
We remain optimistic that in the current gold price environment, the
Young-Davidson mine will be generating positive free cash flow by the
end of this year."
Young-Davidson Update
-
At the end of the quarter, the Young-Davidson mine achieved 557 days of
lost time incident free operations.
-
Production of 40,538 gold ounces for the quarter represented the ninth
consecutive quarter of record gold production with the operation
expected to deliver additional period-over-period production increases
going forward as the underground mine ramps-up to targeted levels.
-
Underground cash costs for the quarter decreased to $656 per gold ounce,
an 18% decline over the prior quarter, primarily driven by increased
production, lower unit processing costs and lower underground unit
mining costs. Total cash costs for the quarter, which includes the
low-grade open pit stockpile, decreased by 17% to $723 per gold ounce.
-
During the quarter, underground mine productivity exceeded planned
levels and averaged approximately 3,752 tonnes per day at grades
in-line with reserve grade estimates. With underground productivity at
approximately 94% of the year-end target, the operation is well
positioned to achieve the year-end target of 4,000 tonnes per day and
an ultimate productivity level of 8,000 tonnes per day at the end of
2016.
-
For the third full quarter of underground commercial production, unit
mining costs declined to approximately $41 per tonne, in-line with the
year-end target of $40 per tonne.
-
During the quarter, underground development advance continued at planned
levels with approximately 3,269 metres completed, an average of 36
metres per day. The Company will continue to focus on advancing
underground development to best position the mine for sustainable,
period-over-period, productivity increases in the fourth quarter and
beyond.
-
During the quarter, the mill facility averaged 7,670 tonnes per day,
including 4-days of downtime for scheduled mill reline activities.
Recoveries increased over prior periods to a record 90%, which is
expected to be sustained going forward.
-
As planned, the short life open pit mine was fully depleted in early
June and as a result, during the quarter higher grade underground mill
feed was supplemented with low grade open pit stockpiled ore to ensure
the mill processing facility was operating at peak capacity. The open
pit stockpile will continue to supplement underground ore feed to the
mill processing facility as the underground mine ramps up to targeted
levels and the remaining stockpile will be processed at the end of the
mine life.
-
Currently, approximately 2.6 million tonnes of open pit ore, at an
average grade of approximately 0.80 grams per tonne, is stockpiled
ahead of the mill facility for future processing. As the related mining
costs associated with the stockpile were expended in prior periods, the
processing of this ore will favourably augment the mine's free cash
flow profile going forward.
El Chanate Update
-
During the quarter, the open pit mining rate averaged 94,643 tonnes per
day with mined grades being in-line with plan.
-
Mining operations in the third quarter reflected a transition from the
sequencing of lower grade mining areas to higher grade mining areas
during the latter part of the quarter.
-
Production increased over the prior quarter while cash costs for the
quarter were $663 per ounce, which is in-line with guidance levels.
About AuRico Gold
AuRico Gold is a leading Canadian gold producer with mines and projects
in North America that have significant production growth and
exploration potential. The Company is focused on its core operations
including the Young-Davidson gold mine in northern Ontario, and the El
Chanate mine in Sonora State, Mexico. AuRico's project pipeline also
includes advanced development opportunities in Mexico and Canada.
AuRico's head office is located in Toronto, Ontario, Canada.
Cautionary Statement
This press release contains forward-looking statements and
forward-looking information as defined under Canadian and U.S.
securities laws. All statements, other than statements of historical
fact, are forward-looking statements. The words "expect", "believe",
"anticipate", "will", "intend", "estimate", "forecast", "budget" and
similar expressions identify forward-looking statements.
Forward-looking statements include information as to strategy, plans or
future financial or operating performance, such as the Company's
expansion plans, project timelines, production plans, projected cash
flows or capital expenditures, cost estimates, projected exploration
results, reserve and resource estimates and other statements that
express management's expectations or estimates of future performance.
Forward-looking statements are necessarily based upon a number of
factors and assumptions that, while considered reasonable by
management, are inherently subject to significant uncertainties and
contingencies. Known and unknown factors could cause actual results to
differ materially from those projected in the forward-looking
statements, including: uncertainty of production and cost estimates;
fluctuations in the price of gold and foreign exchange rates; the
uncertainty of replacing depleted reserves and the possible
recalculation or reduction of reserves and resources; the risk that the
Young-Davidson shaft will not perform as planned; the risk that mining
operations do not meet expectations; the risk that projects will not be
developed according to budgets or timelines, changes in laws in Canada,
Mexico and other jurisdictions in which the Company may carry on
business; risks of obtaining necessary licenses, permits or approvals
for operations or projects such as Kemess; disputes over title to
properties; the speculative nature of mineral exploration and
development; risks related to aboriginal or Ejido title claims;
compliance risks with respect to current and future environmental
regulations; disruptions affecting operations; opportunities that may
be pursued by the Company; employee relations; availability and costs
of mining inputs and labor; the ability to secure capital to execute
business plans; volatility of the Company's share price; continuation
of the dividend and dividend reinvestment plan; the effect of future
financings; litigation; risk of loss due to sabotage and civil
disturbances; the values of assets and liabilities based on projected
future cash flows; risks arising from derivative instruments or the
absence of hedging; adequacy of internal control over financial
reporting; changes in credit rating; and the impact of inflation.
Actual results and developments are likely to differ, and may differ
materially, from those expressed or implied by the forward-looking
statements contained herein. Such statements are based on a number of
assumptions which may prove to be incorrect, including assumptions
about: business and economic conditions; commodity prices and the price
of key inputs such as labour, fuel and electricity; credit market
conditions and conditions in financial markets generally; revenue and
cash flow estimates, production levels, development schedules and the
associated costs; ability to procure equipment and supplies and ability
to do so on a timely basis; the timing of the receipt of permits and
other approvals for projects and operations; the ability to attract and
retain skilled employees and contractors for the operations; the
accuracy of reserve and resource estimates; the impact of changes in
currency exchange rates on costs and results; interest rates; taxation;
and ongoing relations with employees and business partners. The Company
disclaims any intention or obligation to update or revise any
forward-looking statements whether as a result of new information,
future events or otherwise, except as required by applicable law.
SOURCE AuRico Gold Inc.
PDF available at: http://stream1.newswire.ca/media/2014/10/14/20141014_C7501_DOC_EN_43002.pdf